Construction diary La Manche от 02.07.2021
Construction progress of the club house LA MANCHE.
In sections 1 and 2 - the floor slab above the 4th floor is 100% ready.
In section 3 - we carry out the reinforcement of the floor slab on the 4th floor.
In section 4 - the vertical elements of the 4th floor were concreted by 85%.
In sections 5 and 6, the brickwork of the 6th floor was completed. Laying of the 7th and 8th floors in progress. Monolithic work completed.
Section 7 - monolithic works and brickwork are completely finished. The ventilation blocks have already been brought to the roof. Roofing work is still underway. Glazing is in progress at the 9th floor.