Latest news from the construction site of the LA MANCHE club residence:
Section 1 - concreting of the 6th floor slab continues. Installation of ventilation units on the 4th floor is completed.
Section 2 - work is underway to reinforce the slab of the 6th floor. Installation of ventilation blocks on the 4th floor is 50% completed.
Section 3 - the concreting of the elements of the 6th floor is nearing completion.
Section 4 - in parallel with the concrete work, the ventilation blocks of the 2nd and 3rd floors are being installed.
Section 5 - monolithic works on all floors have been completed, roofing works have begun. Bricklaying is performed from the 1st to the 4th floor.
Section 6 - work is being actively carried out on the arrangement of engineering and plumbing networks. Glazing works are in progress on all floors.
Section 7 - monolithic work is 100% completed. On the 8th and 9th floors, the lift shafts are being actively prepared for the installation of elevators. Glazing works are also carried out on all floors.