Construction progress as of 20 July 2023

20.07.2023

Summer construction season on La Manche — July 2023

Section #2, 3, 4

- Masonry work has been finalized on the basement floors.

Sections #3, 4

- Completed the installation of transparent aluminum structures (window frames) from the 1st to the 9th floor.

- Installation and insulation of heat water supply pipes is 100% completed.

Section #5

- Aluminum constructions of elevator shafts and stairwells are installed.

- Works are being carried out on the decoration of elevator shafts.

Section #6

- The walls were insulated with mineral wool and the finishing coating was applied. Work continues on other floors.

- The facade of the 1st and 2nd floors is already decorated with granite.

- Work is ongoing on the decoration of the facade with ceramic granite and decorative elements from the 3rd to the 9th floor.

Section #7

- The hinged ventilated overhanging facade of 1-2 floors was decorated with granite.

- Decorative elements of the facade and decoration with ceramic granite are installed from the 3rd to the 9th floor.

- The insulation and decoration of the walls of the 10th floor has been completed.

Parking

- Active earthworks.

- The construction of the entrance ramp to the parking lot is being completed.

- Monolithic works on the arrangement of the grid, vertical elements and floor slabs are being carried out.