Autumn history of the construction of La Manche
La Manche has already illuminated Podil with its facade lights this month. The facade is clearly visible among the surrounding space. The interior works already fill it with future coziness and comfort.
Section IV
- Installation of heat supply pipes is completed
Section V
- We carry out work on the installation of double-glazed windows from the 1st to the 5th floor
- Installed window frames
- 1 installation of aluminum window and door frames.
- Mounted aluminum structures stained glass windows on stairwells and elevator shafts.
Section VII
- Finishing of the hinged ventilated facade with granite along the street has been completed. Naberezhno-Khreshchatytska embankment
- Completed plastering works in MZK from 2nd to 10th floors
- Scaffolding was installed for facade works on the street. Shchekavytska
- Installation of storm sewer pipes was carried out
Section VII
- The outer part of the hinged ventilated facade was decorated with granite along the street. Naberezhno-Khreshchatytska embankment
- Finished plastering works in MZK from 2nd to 10th floors
- Workers are installing the internal facade from the 2nd to the 10th floor
- The volume of storm sewers has already been completed by 100%.
Parking
- Excavation and monolithic works are being carried out for the arrangement of the exit ramp from the parking lot