Section 1 - The 7th to the 9th floors brickwork is underway. The installation of the main roof elements has been completed.
Section 2 - The 7th to the 9th floors brickwork is underway. Work on the installation of metal roof formwork is in progress.
Section 3-4 - The 2nd to the 4th floors brickwork is underway. The work on the boiler room in the fourth section has been completed.
Section 5 - The 8-9th floors glazing is in progress. The 1st-floor brickwork is underway. Balconies floor cement screed application is at the final stage.
Section 6-7 - Facade works are in progress. Glazing, masonry work, and floor cement screed application are 100% complete. Network installation has been completed.
The underground parking level monolithic works are in progress.