Construction progress as of 27 August 2021

27.08.2021

La Manche club residence latest construction news.

Section 1 - The 8th-floor vertical constructions installation is now underway.

Section 2 - The reinforcement of the 8th floor vertical constructions has been completed.

Section 3 - Monolithic works on the floor slab panel above the 7th floor have been completed.

Section 4 - The construction of the floor slab panel above the 7th floor is 30% complete. Concreting works are in progress.

Section 5 - Monolithic works have been completed. The brickwork on every floor is now underway.

Section 6 - The glazing and plumbing systems installation on every floor are in progress

Section 7 - The application of floor cement screed on the 4th to 6th floor is underway. Roof installation and facade insulation are in progress.