Construction progress as of 31 August 2025

31.08.2025

Despite the difficult situation in the country and the forced concentration of resources on other sites, work at the La Manche construction site continues

Glazing

99% of glazing completed (sections 2–5)

Window glazing completed in sections 1–2

Facade works

Section 6 – facade works completed

Section 5 – brick plastering completed, embedded elements for facade guides installed; facade works are ongoing, the next stage is insulation

Interior works

Section 5 – electrical works completed prior to plastering

Section 5 – plastering of the stairwell carried out (from 2nd to 10th floor)

Section 7 – the show floor has been updated and finalized (interior solutions, finishing touches)

The company is working on optimizing processes. In the near term, the priority will be completing the facade of section 5 and actively continuing interior works