Despite the difficult situation in the country and the forced concentration of resources on other sites, work at the La Manche construction site continues
Glazing
99% of glazing completed (sections 2–5)
Window glazing completed in sections 1–2
Facade works
Section 6 – facade works completed
Section 5 – brick plastering completed, embedded elements for facade guides installed; facade works are ongoing, the next stage is insulation
Interior works
Section 5 – electrical works completed prior to plastering
Section 5 – plastering of the stairwell carried out (from 2nd to 10th floor)
Section 7 – the show floor has been updated and finalized (interior solutions, finishing touches)
The company is working on optimizing processes. In the near term, the priority will be completing the facade of section 5 and actively continuing interior works
(Українська) Компанія працює над оптимізацією процесів. У найближчій перспективі головним завданням стане завершення фасаду секції 5 та активне продовження внутрішніх робіт.