Construction progress as of 14 October 2025

14.10.2025

Section 5

Interior and façade works are in progress: plastering has been completed, installation of engineering systems has begun, and preparation for the screed is underway.

The façade has been insulated with two layers of mineral wool, 50 mm each, and guides for the ventilated façade are being installed.

Sections 3–4

Similar works will start here soon — plastering, installation of utilities, insulation, and preparation for decorative finishing.

Sections 6–7 — finishing works are in progress.

Sections 1–2 — installation of engineering systems and doors.

Sections 3, 4, and 5 — approaching the final stage of façade works.