(044) 299 49 66

Construction progress as of 01 April 2026

01.04.2026

Due to the improvement of weather conditions in the La Manche clubhouse, the pace of work has increased. For March 2026:

In section 3

- the installation of the electrical network in the MZK and on the stairwells has been completed.

- plans for April - installation of water and heating networks, floor screed and plastering.

In section 4

- the installation of water and heating networks from floors 2 to 7 has been completed.

- plans for April - to complete the installation of networks on other floors and perform floor screed.

In section 5

- facade work is ongoing, currently the installation of porcelain stoneware is underway.