The La Manche clubhouse in Podil continues to gradually move towards completion! Although weather conditions have slowed down the construction process, work is underway here that does not require compliance with temperature regimes.
Since December 15 and currently at the site:
- Installation of slopes around windows and balcony doors continues (sections 4 and 5)
- Facade work continues - installation of brackets, aluminum subsystems and fastening of porcelain tiles (sections 4 and 5)
- Electrical cabinets installed (section 4)
- Section 4 is insulated with mineral wool in two layers of 10 and 5 cm from floors 8 to 3
- Installation of drainage plastic pipes for drainage from balconies continues Section 4