Construction progress as of 06 July 2026

06.07.2026

In June, a significant portion of the planned works was completed:

Section 1

- electrical network installation in common areas and stairwells completed from the 10th to the 1st floor

Section 2

- electrical network installation completed in common areas

- plastering of common areas completed from the 10th to the 3rd floor

Section 3

- plastering completed in common areas and stairwells

- water supply and heating pipelines installed from the 10th to the 2nd floor

Parking

- formwork installed and Ø100 mm corrugated cable mounted in the electrical room on Level -1

Façade

- installation of porcelain stoneware cladding and decorative elements is ongoing

- balcony waterproofing on the Shchekavytska Street side and installation of roof drainage outlets are in progress