In June, a significant portion of the planned works was completed:
Section 1
- electrical network installation in common areas and stairwells completed from the 10th to the 1st floor
Section 2
- electrical network installation completed in common areas
- plastering of common areas completed from the 10th to the 3rd floor
Section 3
- plastering completed in common areas and stairwells
- water supply and heating pipelines installed from the 10th to the 2nd floor
Parking
- formwork installed and Ø100 mm corrugated cable mounted in the electrical room on Level -1
Façade
- installation of porcelain stoneware cladding and decorative elements is ongoing
- balcony waterproofing on the Shchekavytska Street side and installation of roof drainage outlets are in progress