Construction progress as of 04 May 2026

04.05.2026

Due to the improvement of weather conditions in the La Manche clubhouse, the pace of work has increased. For March 2026:

In section 3

- the installation of the electrical network in the MZK and on the stairwells has been completed.

- plans for April - installation of water and heating networks, floor screed and plastering.

In section 4

- the installation of water and heating networks from floors 2 to 7 has been completed.

- plans for April - to complete the installation of networks on other floors and perform floor screed.

In section 5

- facade work is ongoing, currently the installation of porcelain stoneware is underway.

(Українська) - виконано частину декоративних елементів навколо вікон і накривки на перегородках з АКП