Construction progress as of 08 November 2021

08.11.2021

La Manche club residence latest construction news

Section 1 - Concreting of the floor slab above the 9th floor is underway.

Section 2 - The installation of the 9th floor vertical elements is 100% complete. The installation of floor slab formwork has started.

Section 3 - The 9th-floor vertical elements concrete is 70% set.

Section 4 - The installation of the floor slab above the 9th floor has been completed. The 9th-floor elements reinforcement is underway.

Section 5 - All floors' internal brickwork is in progress. Sewer risers installation is now underway.

Section 6 - The internal works such as electricity network and ventilation units installation as well as application of the 6th-floor cement screed are in progress. Facade glazing is now underway.

Section 7 - Works on future apartments insulation have been almost completed. The installation of the facade elements is now underway. The application of floor cement screed has been completed on all floors. The panoramic elevator has been installed.