This spring, the interior of the complex is filled with elevator works. There, flooring is being installed in elevator shafts, control equipment is being delivered and installed. Specialists are carefully testing and adjusting the operation of all system components.
In general, active works:
◽️Section II
Installation of aluminum frames of window structures from the 2nd to the 8th floors is being carried out, with a total volume of 84 structures.
Stained glass systems of the staircase and elevator part of the section are being manufactured.
◽️Section IV
We are installing elevators in the section.
We are performing work on commissioning and adjusting elevators.
We are reinforcing the monolith of the reinforced concrete grillage of the ramp to the parking lot, a total volume of 120 m3 of concrete.