Construction progress as of 31 December 2021

31.12.2021

Section 1- the 8th and 9th floors masonry work has started. Plumbing system installation is now underway.

Section 2 - Monolithic works have been completed. Roof installation is in progress. Ventilation units installation is at the final stage.

Section 3 - The 2nd and 3rd floors masonry works are now underway.

Section 4 - Reinforcement of the floor slab above the boiler room is in progress.

Section 5 - Residential premises masonry works have been completed, a metal roof installation is underway.

Section 6 - Monolithic and masonry works, as well as the application of floor cement screed, have been completed. The elevators installation is underway.

Section 7 - Glazing and plumbing works have been completed. Facade works and electricity network installation are in progress.

The underground parking level monolithic works are now underway.