Section 1- the 8th and 9th floors masonry work has started. Plumbing system installation is now underway.
Section 2 - Monolithic works have been completed. Roof installation is in progress. Ventilation units installation is at the final stage.
Section 3 - The 2nd and 3rd floors masonry works are now underway.
Section 4 - Reinforcement of the floor slab above the boiler room is in progress.
Section 5 - Residential premises masonry works have been completed, a metal roof installation is underway.
Section 6 - Monolithic and masonry works, as well as the application of floor cement screed, have been completed. The elevators installation is underway.
Section 7 - Glazing and plumbing works have been completed. Facade works and electricity network installation are in progress.
The underground parking level monolithic works are now underway.