Construction progress as of 27 March 2024

27.03.2024

◽️Section V

Installation of 2 elevators of the section

Finishing of 2 elevator shafts has been completed

◽️Section IV

Installation of elevator equipment has been completed

Finalization of decoration of 2 elevator shafts

Window structures (stained glass windows) have been installed in the elevator shafts

Installation of double-glazed windows is 100% complete

◽️Section III

Materials have been delivered and work on glazing the section is being finalized

Installation of 95% of the total volume of the section windows