Construction progress as of 30 November 2021

30.11.2021

LA MANCHE club residence construction process for December 1st, 2021

Section 1 - All monolithic works have been completed. Roofing installation is underway.

Section 2 - Monolithic parapets installation is at the final stage. Ventilation units installation is in progress.

Section 3 - Monolithic works on the 10th-floor floor slab are at the final stage.

Section 4 - The boiler room vertical structures reinforcement and 2-3rd floors external walls brickwork are now underway.

Section 5 - Masonry work has almost been completed.

Section 6 - The 8-9th floors metal roof installation is in progress. Balconies waterproofing and screed application are now underway.

Section 7 - Facade works are in progress.