(044) 299 49 66

Construction progress as of 04 August 2026

04.08.2026

La Manche club house is steadily moving towards completion. In July, a significant amount of internal work was completed at the site, including:

Section 1

- Wall plastering in common areas (2nd to 10th floors) is completed

- Horizontal piping for water supply and heating in corrugated conduits (2nd to 10th floors)

Section 2

- Wall plastering in common areas up to the 2nd floor has been completed

Section 3

- Cement-sand floor screed has been laid (10th to 2nd floors)

Section 4

- Waterproofing of balconies on the Shchekavytska Street side is ongoing

- Insulation around windows, balconies, and on the facade is completed

- Tile installation on the facade, balconies, and parapets is in progress

- Decorative elements on balconies (3rd to 7th floors) have been installed