Construction progress as of 03 September 2026

03.09.2026

In August, construction work continued at the La Manche club house site. During the month, a significant volume of planned works was completed across all sections:

Section 1

- Apartment-by-apartment piping for water and heat supply, as well as floor screed, executed from the 2nd to 7th floors

- Screed completed in the transformer substation at level -3.900 (-1st floor)

Section 2

- Apartment-by-apartment piping for water and heat supply executed from the 2nd to 7th floors

- Laying of cement-sand screed has begun

Section 3

- Apartment doors, as well as utility doors and concealed access hatches, installed from the 2nd to 8th floors

Section 4

- Insulation of balcony undersides with mineral wool is ongoing from the 3rd to 9th floors

- Insulation of balcony ends with polystyrene is ongoing

- Balcony waterproofing executed and storm drainage funnels installed from the 2nd to 8th floors

Section 5

- Installation of decorative elements around door and balcony units completed, along with decorative plastering and painting of balcony undersides from the 3rd to 8th floors