Although the building suffered external damage as a result of a Russian shelling attack, interior works continued according to schedule. For May 2026:
Section 5
- Apartment doors installed up to the 8th floor.
Section 4
- Concealed technical doors installed from the 2nd to the 8th floors; apartment doors from the 2nd to the 4th floors.
- Drilling of openings in balcony concrete for waterproofing and rainwater drainage funnels.
Section 3
- Installation of Gemafoam from the 2nd to the 10th floors for subsequent installation of water supply and heating networks.
Section 2
- Installation of electrical networks in common areas for lighting has been completed.
Section 1
- Works on installation of electrical networks in common areas have started.