Construction progress as of 08 June 2026

08.06.2026

Although the building suffered external damage as a result of a Russian shelling attack, interior works continued according to schedule. For May 2026:

Section 5

- Apartment doors installed up to the 8th floor.

Section 4

- Concealed technical doors installed from the 2nd to the 8th floors; apartment doors from the 2nd to the 4th floors.

- Drilling of openings in balcony concrete for waterproofing and rainwater drainage funnels.

Section 3

- Installation of Gemafoam from the 2nd to the 10th floors for subsequent installation of water supply and heating networks.

Section 2

- Installation of electrical networks in common areas for lighting has been completed.

Section 1

- Works on installation of electrical networks in common areas have started.