(044) 299 49 66

Construction diary La Manche от 02.07.2021

08
02

Construction progress of the club house LA MANCHE.

In sections 1 and 2 - the floor slab above the 4th floor is 100% ready.

In section 3 - we carry out the reinforcement of the floor slab on the 4th floor.

In section 4 - the vertical elements of the 4th floor were concreted by 85%.

In sections 5 and 6, the brickwork of the 6th floor was completed. Laying of the 7th and 8th floors in progress. Monolithic work completed.

Section 7 - monolithic works and brickwork are completely finished. The ventilation blocks have already been brought to the roof. Roofing work is still underway. Glazing is in progress at the 9th floor.

Choose an apartment