Сonstruction diary La Manche від 19.05.2021

08
02

The current status of the construction of the club house LA MANCHE

In section 1, the vertical elements of the 3rd floor were concreted by 50%.

Section 2 - the floor slab above the 2nd floor is 100% complete.

Section 3 - the reinforcement of the floor slab above the 2nd floor is 80% complete.

In section 4 - the installation of the formwork of the floor slab above the 2nd floor is 60% done.

In section 5 - all 9 floors are finished, we continue the brickwork at the level of the 4th floor.

In section 6 - now we are laying the 6th, 7th and 8th floors with bricks.

Section 7 - monolithic work and brickwork are fully completed. The ventilation blocks have already been brought to the roof. Roofing work in progress.