Diary of the construction of the English Channel from 22.07.2021

08
02

Current information from the construction site of the club house LA MANCHE.

Section 1 - concreting of the floor slab of the 5th floor continues.

Section 2 - vertical structures of the 5th floor are 100% finished. Works on reinforcement of the floor slab of the 5th floor are being performed.

Section 3 - work on reinforcement of future vertical structures continues.

Section 4 - pouring a concrete mixture of vertical structures on the 5th floor is made by 50%.

Section 5 - started work on masonry ventilation structures. In the process of glazing windows from the 2nd to the 9th floor.

Section 6 - internal brick works are underway, which are already 50% complete. There is also glazing of windows from the 2nd to the 9th floor.

Section 7 - masonry of external and internal walls of the first floor. At the same time, doors and windows are being installed from the 2nd to the 9th floor. Work is underway to install a metal roof on the facade and install sewer risers on all floors. Start of laying and installation of power grids.